Question 10

Multiple Choice

Which of these is the best guideline for determining how far a team should go in breaking down the WBS?


A) Each work package should require between 1-8 hours to complete,
B) Each work package should require between 8 and 800 hours to complete.
C) If it is useful for planning, accountability, or control purposes to break a task down into smaller component parts, then do so.
D) The level of detail the project team uses in planning a project should match the level of detail it uses for control.
E) None of the above

Correct Answer: