Which of these is the best guideline for determining how far a team should go in breaking down the WBS?
A) Each work package should require between 1-8 hours to complete,
B) Each work package should require between 8 and 800 hours to complete.
C) If it is useful for planning, accountability, or control purposes to break a task down into smaller component parts, then do so.
D) The level of detail the project team uses in planning a project should match the level of detail it uses for control.
E) None of the above
Correct Answer:
Verified
Q3: Which of the following is a reasonable
Q4: All of the following are advantages to
Q5: Which of the following depends) on the
Q6: Which of the following WBS formats is
Q7: A consumer electronics company is planning a
Q8: Which of the following is not a
Q9: A new project manager is taking over
Q11: A national circus organization performs in outdoor
Q12: Which WBS approach is most likely to
Q13: Your school's recruiting staff is planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents