Which of the Following Is Not a Characteristic of Mind

Question 8

Multiple Choice

Which of the following is not a characteristic of mind mapping as a tool for WBS development?


A) Mind mapping stimulates creative thinking about the project's activities.
B) Mind mapping engages the team.
C) Mind mapping helps generate enthusiasm and commitment to the project.
D) The nonlinear nature of the mind mapping process brings out fewer ideas than outlining.
E) Because mind mapping does not involve sequencing or priorities, mind mapping steers people away from potential disagreements about what or who is most important.
F) None of the above.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents