Which of the Following Is a Reasonable Way to Determine

Question 3

Multiple Choice

Which of the following is a reasonable way to determine the learning rate for a project?


A) Ask people who will do the work to estimate the learning rates of other team members.
B) Use the PERT method.
C) Find historical, internal data for similar projects.
D) Benchmark against learning rates for projects of all types within the organization.
E) Use whatever learning rate is specified by the customer
F) All of the above
G) None of the above

Correct Answer:

verifed

Verified