An easy way to assess team member interest in various aspects of a project before assigning responsibility is:


A) Create a responsibility matrix and fill in people's names.
B) Have each team member use a separate color during mind mapping and then look at the pen colors on the WBS mind map and see where team members' dominant interests seem to be.
C) Conduct an email survey.
D) Use a project-involvement matrix.
E) Create an OBS.