Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?
A) Total time is 13 days, total cost is $1,500.
B) Total time is 12 days, total cost is $2,000.
C) Total time is 12 days, total cost is $2,300.
D) Total time is 11 days, total cost is $1,850.
E) Total time is 11 days, total cost is $2,350.
Correct Answer:
Verified
Q75: You have just performed a CPM analysis
Q76: You have just used the network planning
Q77: You have just used the network planning
Q78: Which of the following is not an
Q79: You have collected the data for a
Q81: This is usually a written description of
Q82: Pieces of work within a project that
Q83: A project has four activities: A, B,
Q84: Which of the following is not an
Q85: A project has four activities: A, B,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents