You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.
At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:
Verified
Q74: A company must perform a maintenance project
Q75: You have just performed a CPM analysis
Q76: You have just used the network planning
Q77: You have just used the network planning
Q78: Which of the following is not an
Q80: Here are the data for a time-cost
Q81: This is usually a written description of
Q82: Pieces of work within a project that
Q83: A project has four activities: A, B,
Q84: Which of the following is not an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents