You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level. What should be that time (in days and round to the nearest whole number) ?
A) 40
B) 13
C) 37
D) 29
E) 53
Correct Answer:
Verified
Q72: In CPM analysis, it is generally expected
Q73: You have just used the network planning
Q74: A company must perform a maintenance project
Q75: You have just performed a CPM analysis
Q76: You have just used the network planning
Q78: Which of the following is not an
Q79: You have collected the data for a
Q80: Here are the data for a time-cost
Q81: This is usually a written description of
Q82: Pieces of work within a project that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents