You have just used the network planning model and found the critical path length is 60 days and there are two critical paths. The standard deviation of the first critical path is 10 days and the s.d. of the second critical path is 15 days. The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy) .
A) 0.84
B) 0.25
C) 0.16
D) 0.75
E) 0.66
Correct Answer:
Verified
Q68: For an activity in a CPM analysis,
Q69: A listing of immediate predecessor activities is
Q70: In this structure, team members are assigned
Q71: You know when you have arrived at
Q72: In CPM analysis, it is generally expected
Q74: A company must perform a maintenance project
Q75: You have just performed a CPM analysis
Q76: You have just used the network planning
Q77: You have just used the network planning
Q78: Which of the following is not an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents