A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
A) It specifies the relationships in the CPM network of activities.
B) It provides useful timing information.
C) It includes cost information.
D) It is the probability information required in the final step of CPM.
E) None of these choices are correct
Correct Answer:
Verified
Q64: A structure for organizing a project where
Q65: Popular project management software used in mid-sized
Q66: You have the following time and cost
Q67: In this structure, each project uses people
Q68: For an activity in a CPM analysis,
Q70: In this structure, team members are assigned
Q71: You know when you have arrived at
Q72: In CPM analysis, it is generally expected
Q73: You have just used the network planning
Q74: A company must perform a maintenance project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents