Solved

For an Activity in a CPM Analysis, the Early Start

Question 68

Multiple Choice

For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?


A) The late finish is 12.
B) The early finish is 10.
C) The slack for this activity is 2.
D) The duration of this activity is 2.
E) The activity is on the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents