For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?
A) The late finish is 12.
B) The early finish is 10.
C) The slack for this activity is 2.
D) The duration of this activity is 2.
E) The activity is on the critical path.
Correct Answer:
Verified
Q63: You have collected the data for a
Q64: A structure for organizing a project where
Q65: Popular project management software used in mid-sized
Q66: You have the following time and cost
Q67: In this structure, each project uses people
Q69: A listing of immediate predecessor activities is
Q70: In this structure, team members are assigned
Q71: You know when you have arrived at
Q72: In CPM analysis, it is generally expected
Q73: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents