You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?
A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.
Correct Answer:
Verified
Q66: You have the following time and cost
Q67: In this structure, each project uses people
Q68: For an activity in a CPM analysis,
Q69: A listing of immediate predecessor activities is
Q70: In this structure, team members are assigned
Q72: In CPM analysis, it is generally expected
Q73: You have just used the network planning
Q74: A company must perform a maintenance project
Q75: You have just performed a CPM analysis
Q76: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents