Which of the following statements regarding PERT analysis is NOT true?
A) Each activity has three estimates of its duration.
B) Project variance is the sum of all critical activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) The most likely time is different from the expected activity time.
Correct Answer:
Verified
Q90: In a PERT network, non-critical activities that
Q91: The bell curve is often appropriate for
Q92: The beta distribution is used in project
Q93: Variation in activities that are not on
Q94: A local project being analyzed by PERT
Q96: The time an activity will take assuming
Q97: An activity on a PERT network has
Q98: An activity on a PERT network has
Q99: A PERT project has 45 activities, 19
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents