A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 114 and 120?
A) 0.84134
B) 0.22663
C) 0.34134
D) 0.47725
E) 0.27337
Correct Answer:
Verified
Q94: A local project being analyzed by PERT
Q95: Which of the following statements regarding PERT
Q96: The time an activity will take assuming
Q97: An activity on a PERT network has
Q98: An activity on a PERT network has
Q100: Which of the following statements regarding PERT
Q101: A project whose critical path has an
Q102: A project manager determined that the project
Q103: A network consists of the following list.
Q104: Two activities on the same critical path
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents