Question 81
Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) . Assume no working-day holidays during the months of May and June-no Memorial Day holiday, for example.
Question 82
Multiple Choice
Since resource leveling or smoothing delays noncritical activities, a common result is an increase in network ___________.
Question 83
Multiple Choice
Without a __________ budget a good project schedule and cost control are impossible.
Question 84
Multiple Choice
When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called _________.
Question 85
Multiple Choice
A project cost baseline is also called __________.
Question 86
Multiple Choice
After resource leveling or smoothing, one goal is that the amount of resources needed over the life of the project will be ___________.
Question 87
Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. The project is time-constrained and the project manager wishes to minimize the number of resources required at any given time. Each activity requires a single resource.
Question 88
Multiple Choice
Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
Question 89
Multiple Choice
In reality resource allocation generally occurs in a(n) ___________ environment where the demands of one project have to be reconciled with the needs of other projects.
Question 90
Multiple Choice
When a project is classified as resource-constrained, a resource constraint exists, and positive slack is insufficient, then the project duration is typically __________.
Question 91
Multiple Choice
When using the _______ scheduling technique, startup and shutdown costs are major considerations.
Question 92
Multiple Choice
In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions.
Question 93
Multiple Choice
__________ is a technique that can be used to quickly solve the combinational problem of resource allocation.
Question 94
Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node.
Question 95
Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource.
Question 96
Multiple Choice
When classifying projects, ________ constrained means that the amount of a specific resource is fixed and the duration of the project is flexible.
Question 97
Multiple Choice
In terms of project classification, ________ constrained means that project duration is fixed and resources are flexible.
Question 98
Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) .