Question 121
Multiple Choice
Although they do not guarantee optimal solutions, _____ are useful in finding reasonable solutions when the number of possible options is overwhelming.
Question 122
Multiple Choice
3D printing is also known by this name?
Question 123
Multiple Choice
Which of the following does not reflect sustainable production?
Question 124
Multiple Choice
Which of the following does not reflect lean process design general principles?
Question 125
Multiple Choice
What is it about job shops that make them appropriate for products in the introductory phase of their life cycle?
Question 126
Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load meter moved. An analyst has prepared the following flow and distance matrices:
What is the distance (in meters) from area III to area I of this new facility?
Question 127
Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load meter moved. An analyst has prepared the following flow and distance matrices:
Which layout will minimize the total distance loads will be moved each week?
Question 128
Multiple Choice
Which of the following process types would be most likely to be used in the maturity phase of a product's life cycle?
Question 129
Multiple Choice
Which of the following process types would be most likely to be used in the introductory phase of a product's life cycle?
Question 130
Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load per meter moved. An analyst has prepared the following distances and flow matrices:
How many least costly process layouts are there?
Question 131
Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load meter moved. An analyst has prepared the following flow and distance matrices:
What is the total flow (loads per week) between department Y and department Z?
Question 132
Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load meter moved. An analyst has prepared the following flow and distance matrices:
If the company were to locate departments X, Y, and Z in areas I, II, and III, respectively, what would be the total distance (in meters) loads would be moved each week?
Question 133
Multiple Choice
A company has an assembly line with 34 tasks. The longest task is 4.7 minutes and the total time for all tasks is 92 minutes. The line will operate for 615 minutes per day.What is the maximum cycle time?