Calculate the Forecasted Cost at Completion If the Cumulative Actual

Question 67

Multiple Choice

Calculate the forecasted cost at completion if the cumulative actual cost is R100 000 and the re-estimate of remaining work to be performed is R50 000.


A) FCAC = R50 000
B) FCAC = R150 000
C) FCAC = 2
D) FCAC = 0.5