Question 41
Multiple Choice
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete) , B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.All jobs are available now and the time now is 0.Using SOT rule sequence the jobs and find the schedule (single machine scheduling problem) .What is the completion time of job B as per your schedule?
Question 42
Multiple Choice
Which of the following priority rules used in scheduling the sequence of production is calculated as the time remaining before the due date minus the remaining processing time, with the smallest value being run first?