Question 1
True/False
Gantt charts typically show how tasks must be ordered and when an activity should begin and end.
Question 2
True/False
The focus of project management is to assure that systems development projects meet customer expectations and are delivered within budget and time constraints.
Question 3
True/False
When a project manager works closely with customers to assure project deliverables meet expectations,he/she is performing a customer relations activity.
Question 4
True/False
In order to determine the resources required for project completion,an organization should analyze the project's scope and determine the project's probability of successful completion.
Question 5
True/False
Task sequence depends on which tasks produce deliverables needed in other tasks,when critical resources are available,the constraints placed on the project by the client,and the process outlined in the SDLC.