Question 101
Multiple Choice
The amount of time that an activity can be delayed without delaying the project refers to:
Question 102
Multiple Choice
What would be the estimated time for completion if time estimates for programming are as follows: optimistic = 4 weeks;pessimistic = 6 weeks;realistic = 5 weeks?
Question 103
Multiple Choice
In OOSAD,one outcome of defining the overall system as a collection of components is:
Question 104
Multiple Choice
Realistic time is:
Question 105
Multiple Choice
What would be the estimated time for completion if time estimates for installation are as follows: optimistic = 1 week;pessimistic = 1 week;realistic = 1 week?
Question 106
Multiple Choice
In OOSAD,each project iteration has all of the following except:
Question 107
Multiple Choice
When a project manager divides a system into components in OOSAD,each component is called a(n) :
Question 108
Multiple Choice
Slack time is equal to:
Question 109
Multiple Choice
Which of the following is a true statement regarding network diagrams?
Question 110
Multiple Choice
In OOSAD,iterations are normally:
Question 111
Multiple Choice
What would be the estimated time for completion if the time estimates for report design are as follows: optimistic = 3 weeks;pessimistic = 9 weeks;realistic = 6 weeks?
Question 112
Multiple Choice
A critical path is:
Question 113
Multiple Choice
Optimistic time is:
Question 114
Multiple Choice
Pessimistic time is:
Question 115
Multiple Choice
Which of the following is true regarding Gantt chart construction?
Question 116
Multiple Choice
Automated tools available to help you manage a development project are referred to as:
Question 117
Short Answer
A ________ is a systems analyst with a diverse set of skills-management,leadership,technical,conflict management,and customer relationship-who is responsible for initiating,planning,executing,and closing down a project.