In the PDM method (circle all that are true) :
A) activities cannot be started before immediate predecessors are completed
B) activities can be repeated
C) activities can be started when immediate predecessors are only partially completed
D) there is more flexibility in scheduling than in the usual finish-to-start method
Correct Answer:
Verified
Q12: The critical path:
A) is shortest path through
Q13: In a start-to-start relationship, a 2-day lag
Q14: The criticism of network techniques that some
Q15: Resource leveling:
A) makes use of float (slack)
Q16: The forward and backward pass:
A) determine the
Q18: Statement: The term "dummy activity" is a
Q19: Statement: Redundant activities are activities that are
Q20: Statement: There can only be one critical
Q21: Statement: If an activity has multiple predecessors,
Q22: Statement: The total slack of each of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents