Resource leveling:
A) makes use of float (slack) to move activities to to time slots other than the "as early as possible" dates.
B) makes the workload on resources more evenly distributed.
C) can potentially turn non-critical activities into critical ones.
D) all of the above.
E) (a) and (b) above.
Correct Answer:
Verified
Q10: The following technique requires the use of
Q11: If Activity A has to be performed
Q12: The critical path:
A) is shortest path through
Q13: In a start-to-start relationship, a 2-day lag
Q14: The criticism of network techniques that some
Q16: The forward and backward pass:
A) determine the
Q17: In the PDM method (circle all that
Q18: Statement: The term "dummy activity" is a
Q19: Statement: Redundant activities are activities that are
Q20: Statement: There can only be one critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents