The criticism of network techniques that some project work cannot be known beforehand can be somewhat overcome by:
A) drawing a Gantt chart.
B) using the AON method.
C) never planning project activities in detail.
D) using a suitable computer system.
E) breaking the project down into phases and planning only the imminent phase in detail.
Correct Answer:
Verified
Q9: The advantages of scheduling include all of
Q10: The following technique requires the use of
Q11: If Activity A has to be performed
Q12: The critical path:
A) is shortest path through
Q13: In a start-to-start relationship, a 2-day lag
Q15: Resource leveling:
A) makes use of float (slack)
Q16: The forward and backward pass:
A) determine the
Q17: In the PDM method (circle all that
Q18: Statement: The term "dummy activity" is a
Q19: Statement: Redundant activities are activities that are
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents