When is the project manager using analogous estimating?
A) The PM doesn't have all of the information needed to give time estimates
B) The PM needs to pad their estimates
C) The PM is using a mathematical model
D) The PM uses similar projects or activities to assist with time estimates
E) The PM is using a Monte Carlo technique
Correct Answer:
Verified
Q11: What is true of corrective action?
A)Action against
Q12: What describes the Executing Process Group?
A)Complete work
Q13: What is a murder board? Select all
Q14: a Work Breakdown Structure (WBS) typically contains
Q15: Select all that apply - a WBS
Q17: When is the project manager using parametric
Q18: Which of the following is common problem
Q19: What does the 50/50 rule of progress
Q20: What does the 20/80 rule of progress
Q21: Kennedy is utilizing the Precedence Diagramming Method
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents