What does the 50/50 rule of progress tracking imply?
A) An activity is considered 50% complete when it is 50% complete.
B) An activity is considered 50% complete when it begins and 100% complete when the activity is completed
C) An activity is consider 50% complete when its successor begins
D) An activity is credited for 50% complete when it half done, and the other 50% when it is complete
Correct Answer:
Verified
Q12: What describes the Executing Process Group?
A)Complete work
Q13: What is a murder board? Select all
Q14: a Work Breakdown Structure (WBS) typically contains
Q15: Select all that apply - a WBS
Q16: When is the project manager using analogous
Q17: When is the project manager using parametric
Q18: Which of the following is common problem
Q20: What does the 20/80 rule of progress
Q21: Kennedy is utilizing the Precedence Diagramming Method
Q22: Michael is looking at a network diagram
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents