When is the project manager using parametric estimation?
A) If the Project Manager is using his instinct to determine the estimated project length
B) If the Project Manager needs to pad their estimates
C) If the Project Manager is using Monte Carlo analysis
D) Using a statistical relationship that exists through historical data or other mathematical relationship
E) None of the above
Correct Answer:
Verified
Q12: What describes the Executing Process Group?
A)Complete work
Q13: What is a murder board? Select all
Q14: a Work Breakdown Structure (WBS) typically contains
Q15: Select all that apply - a WBS
Q16: When is the project manager using analogous
Q18: Which of the following is common problem
Q19: What does the 50/50 rule of progress
Q20: What does the 20/80 rule of progress
Q21: Kennedy is utilizing the Precedence Diagramming Method
Q22: Michael is looking at a network diagram
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents