Which of the Following Project Management Tools Is Used to Identify

Question 5

Multiple Choice

Which of the following project management tools is used to identify the tasks that can be delayed for a certain amount of time without having an effect on the overall schedule?


A) Work Breakdown Structure (WBS)
B) Milestone chart
C) Program and Evaluation Review Technique (PERT) Chart
D) A. and C.