Solved

Which of the Following Project Management Tools Is Used to Evaluate

Question 9

Multiple Choice

Which of the following project management tools is used to evaluate a project's performance and progress by integrating the project scope, schedule and cost?


A) Work breakdown structure (WBS)
B) Performance Evaluation and Review Technique (PERT)
C) Six Sigma SIPOC Diagram
D) Earned Value Management (EVM)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents