Quiz 4: Project Delivery Methods
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 1
Multiple Choice
The term fast track--------
Question 2
True/False
An advantage of the design/build approach is that a firm's fixed price is established before construction begins.
Question 3
True/False
In a pure construction management approach the construction manager usually guarantees the overall price of the project.
Question 4
True/False
In a guaranteed maximum price (GMP) contract, costs above the GMP are covered by the contractor.
Question 5
True/False
A unit-price contract provides an owner with price competition while still allowing for an increase or decrease in actual versus estimated quantities.
Question 6
Multiple Choice
The choice of which delivery method is correct is a factor of perceived risk. Which of the following is a source of project risk?
Question 7
Multiple Choice
Historically, a "master builder" was hired to build a project. Today, the same approach would be most like which delivery method?
Question 8
Multiple Choice
A project is rushed into design without a total understanding of the owner's needs. As the project moves through the design, additional requirements are added, increasing the project budget. This is an example of ????