A work center had planned outputs of 10,15,13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. The cumulative deviation in output is
A) 0
B) 1
C) -1
D) 58
E) unable to determine with given information
Correct Answer:
Verified