For an activity,assume the early start is 3 weeks,early finish is 6 weeks,late start is 4 weeks,and late finish is 7 weeks.What is the activity's slack?
A) 3 weeks
B) 4 weeks
C) 1 week
D) 2 weeks
Correct Answer:
Verified
Q37: A plan to implement a project using
Q38: Popular project management software packages include each
Q39: Boeing used FastTrack for scheduling,tracking,and resource allocation
Q40: Which of the following demands extensive hardware,is
Q41: Advantages of PERT include
A)inexpensive to maintain.
B)flexibility.
C)easy to
Q43: PDM is useful because it provides
A)the start
Q44: Causing a delay to the whole project
Q45: Which of the following is the longest
Q46: Negative slack can occur due to
A)unavailability of
Q47: For an activity,assume the early start is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents