For an activity,assume the early start is 12,early finish is 27,late start is 19,and late finish is 34.What is the activity's slack?
A) 9
B) 6
C) 8
D) 7
Correct Answer:
Verified
Q42: For an activity,assume the early start is
Q43: PDM is useful because it provides
A)the start
Q44: Causing a delay to the whole project
Q45: Which of the following is the longest
Q46: Negative slack can occur due to
A)unavailability of
Q48: Causing a delay to a subsequent activity
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when
Q52: A specific task,or set of tasks,that is