Negative slack can occur due to
A) unavailability of resources.
B) resources were either incorrect or did not do their job right.
C) some activities slipped during project execution.
D) all of the above.
Correct Answer:
Verified
Q41: Advantages of PERT include
A)inexpensive to maintain.
B)flexibility.
C)easy to
Q42: For an activity,assume the early start is
Q43: PDM is useful because it provides
A)the start
Q44: Causing a delay to the whole project
Q45: Which of the following is the longest
Q47: For an activity,assume the early start is
Q48: Causing a delay to a subsequent activity
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when