Question 21
True/False
The valuations in an earned value management analysis must be either profits or revenue.
Question 22
True/False
The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.
Question 23
True/False
Derivative projects are those that address incremental changes to products or processes.
Question 24
True/False
Using the time-cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.
Question 25
True/False
Breakthrough projects are those that provide fundamental improvements to existing products.
Question 26
True/False
Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion.
Question 27
True/False
A project milestone is a specific event to be reached by a particular point in time.
Question 28
True/False
The critical path in a CPM analysis is found by locating the activities times with zero slack.
Question 29
True/False
One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.
Question 30
True/False
In a CPM analysis, if you subtract the early start from the late start, the result is the activity's slack time.
Question 31
True/False
In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time.
Question 32
True/False
One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.
Question 33
True/False
Earned value management (EVM) is a technique for measuring project progress in an objective manner.
Question 34
True/False
When reducing the planned duration of a project using the time-cost CPM model, we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
Question 35
True/False
Earned value management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.
Question 36
True/False
Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.
Question 37
True/False
You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.