Question 41
Short Answer
A negative CV indicates the project is ________ budget.
Question 42
Short Answer
The _________ index measures the project percent complete in relation to the resources that were budgeted.
Question 43
True/False
Because of their easy-to-understand visual format,tracking Gantt charts are the most favored,used,and understandable option for reporting project status.
Question 44
True/False
The baseline is derived from merging information from the work packages with the project network.
Question 45
Short Answer
Given that the AC = 300,PV = 400 and EV = 500,this project is _________ budget.
Question 46
Short Answer
Given a BAC of 5,500 and an EAC of 6,000,the project is expected to be completed _________ budget.
Question 47
True/False
Schedule variance measures progress in time units.
Question 48
Short Answer
Although it is very difficult to measure,measuring ________ performance is as important as measuring schedule and cost performance.
Question 49
True/False
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.