A production line is to be designed for a job with four tasks.The task times are 2.4 minutes,1.4 minutes,0.9 minutes,and 1.7 minutes.After line balancing,the largest possible assigned cycle time is ________ minutes,and the smallest possible assigned cycle time is ________ minutes.
A) 1.8;1.4
B) 1.6;0.9
C) 6.4;2.4
D) 2.4;0.9
E) 6.4;0.9
Correct Answer:
Verified
Q102: The assumptions necessary for a successful product-oriented
Q103: In assembly-line balancing,the theoretical minimum number of
Q105: If the schedule calls for the production
Q107: A production line is to be designed
Q264: One drawback of a product-oriented layout is
Q280: Product-oriented layouts tend to have high levels
Q281: Which one of the following is NOT
Q288: Cycle time is computed as:
A) desired output
Q289: Which of the following is TRUE regarding
Q300: A production line is to be designed
Unlock this Answer For Free Now!