Given the Critical Path Below,calculate the Following

Question 124

Essay

Given the critical path below,calculate the following:
a.The crash cost per unit time savings for each activity.
b.The maximum total crash time savings and cost.
c.The maximum total time-savings with a $3000 budget.
Given the critical path below,calculate the following: a.The crash cost per unit time savings for each activity. b.The maximum total crash time savings and cost. c.The maximum total time-savings with a $3000 budget.

Correct Answer:

verifed

Verified

(a)A saves 1 day for $4000/day,B saves 2...