If a task has free slack it means that the task can be delayed in starting without affecting any other tasks on the schedule.
Correct Answer:
Verified
Q27: The three types of estimates in three-point
Q28: CPM produces three key pieces of information.
Q29: Activity resource estimating, activity duration estimating, and
Q30: In CPM, you calculate task time by
Q31: Crashing a project often adds or removes
Q33: PERT uses a weighted average approach, or
Q34: The critical path is a path through
Q35: Project schedule development determines the planned start
Q36: Time and cost estimates should be done
Q37: Using knowledge of the critical path and