PERT uses a weighted average approach, or beta probability distribution, to capture the three-point estimates (optimistic, most likely, and pessimistic) for activity duration.
Correct Answer:
Verified
Q28: CPM produces three key pieces of information.
Q29: Activity resource estimating, activity duration estimating, and
Q30: In CPM, you calculate task time by
Q31: Crashing a project often adds or removes
Q32: If a task has free slack it
Q34: The critical path is a path through
Q35: Project schedule development determines the planned start
Q36: Time and cost estimates should be done
Q37: Using knowledge of the critical path and
Q38: The critical path method, unlike the critical