Time and cost estimates should be done in a "progressive elaboration" process, meaning they start out general and less accurate and over time become more detailed and accurate as the project proceeds.
Correct Answer:
Verified
Q31: Crashing a project often adds or removes
Q32: If a task has free slack it
Q33: PERT uses a weighted average approach, or
Q34: The critical path is a path through
Q35: Project schedule development determines the planned start
Q37: Using knowledge of the critical path and
Q38: The critical path method, unlike the critical
Q39: COCOMO is an acronym for the Constructive
Q40: Function point analysis can be done at
Q41: _ is defined as the actual amount