Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Determine the minimum cost project factoring in both the costs of expediting and the opportunity cost.What is the duration of the overall minimum cost project?
A) 49 weeks
B) 48 weeks
C) 47 weeks
D) 46 weeks
Correct Answer:
Verified
Q102: Table 11-8
A mad scientist has identified the
Q103: Table 11-8
A mad scientist has identified the
Q104: Table 11-8
A mad scientist has identified the
Q105: Table 11-8
A mad scientist has identified the
Q106: Table 11-8
A mad scientist has identified the
Q108: Consider the tasks, durations, and predecessor relationships
Q109: Consider the project with the following estimates
Q110: Table 11-7
A project manager calculated early and
Q111: A small software development project has five
Q112: Which of these statements is best?
A)PERT is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents