Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.These costs are easy to quantify, but it's difficult to stomach not controlling the world when it's just a matter of a few extra dollars.What's the cost of the minimum duration project?
A) $158,550
B) $163,850
C) $156,350
D) $161,550
Correct Answer:
Verified
Q97: PERT assumes that the total completion time
Q98: Table 11-5 Q99: The crash time of an activity represents Q100: Activity D of a project has a Q101: Table 11-7 Q103: Table 11-8 Q104: Table 11-8 Q105: Table 11-8 Q106: Table 11-8 Q107: Table 11-8
A)the
A project manager calculated early and
A mad scientist has identified the
A mad scientist has identified the
A mad scientist has identified the
A mad scientist has identified the
A mad scientist has identified the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents