Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.These costs are easy to quantify, but it's difficult to stomach not controlling the world when it's just a matter of a few extra dollars.What's the earliest this project can be completed and what would the overall project cost be?
A) 38 weeks
B) 40 weeks
C) 44 weeks
D) 46 weeks
Correct Answer:
Verified
Q101: Table 11-7
A project manager calculated early and
Q102: Table 11-8
A mad scientist has identified the
Q103: Table 11-8
A mad scientist has identified the
Q104: Table 11-8
A mad scientist has identified the
Q105: Table 11-8
A mad scientist has identified the
Q107: Table 11-8
A mad scientist has identified the
Q108: Consider the tasks, durations, and predecessor relationships
Q109: Consider the project with the following estimates
Q110: Table 11-7
A project manager calculated early and
Q111: A small software development project has five
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents