Use the information in the table to determine the early start time for Activity B. 
A) day 10
B) day 8
C) day 9
D) day 11
Correct Answer:
Verified
Q48: An activity has an optimistic time estimate
Q50: What is the early start time for
Q51: What is the slack time for activity
Q53: Use the network diagram and activity lengths
Q54: What is the early finish time for
Q56: What is the slack time for Activity
Q57: An activity has an optimistic time estimate
Q57: What is the float start time for
Q58: What is the early start time for
Q60: What is the slack time for Activity