What is the early start time for Activity G given the activity times and precedence requirements shown in the table? 
A) 14
B) 15
C) 16
D) 17
Correct Answer:
Verified
Q42: An activity has a pessimistic time that
Q45: Use the information in the table to
Q46: Use the information in the table to
Q48: Use the information in the table to
Q49: What is the late finish time for
Q51: What is the slack time for activity
Q53: Use the network diagram and activity lengths
Q54: What is the early finish time for
Q55: Use the information in the table to
Q57: An activity has an optimistic time estimate