Multiple Choice
What is the slack time for activity E? 
A) 1 day
B) 0 days
C) 2 days
D) 4 days
Correct Answer:
Verified
Related Questions
Q42: An activity has a pessimistic time that
Q46: Use the information in the table to
Q48: Use the information in the table to
Q49: What is the late finish time for
Q50: What is the early start time for
Q53: Use the network diagram and activity lengths
Q54: What is the early finish time for
Q55: Use the information in the table to
Q56: What is the slack time for Activity
Q57: An activity has an optimistic time estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents