Multiple Choice
Use the information in the table to determine the early finish time for Activity D. 
A) day 23
B) day 26
C) day 29
D) day 32
Correct Answer:
Verified
Related Questions
Q41: What is the late start time for
Q42: Use the information in the table to
Q42: An activity has a pessimistic time that
Q43: What is the late start time for
Q45: Use the information in the table to
Q48: Use the information in the table to
Q49: What is the late finish time for
Q50: What is the early start time for
Q51: What is the slack time for activity
Q58: Activity Z has estimates a = 5,b
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents