Quiz 8: Cost Estimation and Budgeting
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 1
Essay
Every morning I stumble into the office,turn on the lights and brew a pot of coffee.Sometimes that's all I do and other days I accomplish a great deal.The coffee and light expenses should be classified as ________ costs.
Question 2
True/False
Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
Question 3
True/False
A time-phased budget allocates costs across both project activities and the anticipated time in which the budget is to be expended.
Question 4
Essay
Overhead and selling and administration are classified as ________ costs.
Question 5
True/False
Activity-based costing is based on the notion that projects consume activities and activities consume resources.
Question 6
True/False
A common reason for cost overruns in a project is a low initial estimate of project cost.
Question 7
True/False
A budget contingency of $1 million on a $10 million project means that the project will be planned for a cost of $10 million,but the project organization receives an extra $1 million to guard against unforeseen cost overruns.