A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.
A) 44 days
B) 6 days
C) 17 days
D) 9 days
Correct Answer:
Verified
Q41: Your next project consists of 5 consecutive
Q47: Your next project consists of 10 consecutive
Q62: A project is represented by the activity
Q63: A project consists of four consecutive tasks
Q64: A project is represented by the activity
Q66: CCPM advocates performing all non-critical activities:
A)as late
Q68: Which statement about critical chain methodology is
Q69: A project consists of three activities with
Q71: A project consists of four consecutive tasks
Q72: An important departure from traditional project management
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents