A project consists of three activities with information as shown in the table.What is the overall variance of the project?
A) 4.24
B) 8.41
C) 18
D) 24
Correct Answer:
Verified
Q41: Your next project consists of 5 consecutive
Q47: Your next project consists of 10 consecutive
Q57: Your next project consists of 8 consecutive
Q64: A project is represented by the activity
Q66: CCPM advocates performing all non-critical activities:
A)as late
Q67: A project consists of six consecutive tasks
Q68: Which statement about critical chain methodology is
Q71: A project consists of four consecutive tasks
Q72: An important departure from traditional project management
Q73: A project consists of three activities with