A network consists of the following list. Times are given in weeks.
 Activity  Preceding  Optimistic  Probable  Pessimistic A51114B339C61014DA,B357EB4611 F C6813 G D,E246HF339\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Optimistic } & \text { Probable } & \text { Pessimistic } \\\hline \mathrm { A } & - - & 5 & 11 & 14 \\\hline \mathrm { B } & - & 3 & 3 & 9 \\\hline \mathrm { C } & - - & 6 & 10 & 14 \\\hline \mathrm { D } & \mathrm { A } , \mathrm { B } & 3 & 5 & 7 \\\hline \mathrm { E } & \mathrm { B } & 4 & 6 & 11 \\\hline \text { F } & \mathrm { C } & 6 & 8 & 13 \\\hline \text { G } & \mathrm { D } , \mathrm { E } & 2 & 4 & 6 \\\hline \mathrm { H } & \mathrm { F } & 3 & 3 & 9 \\\hline\end{array} a. Draw the network diagram.
b. Calculate the expected duration and variance of each activity.
c. Calculate the expected duration and variance of the critical path.
d. Calculate the probability that the project will be completed in less than 28 weeks.

Correct Answer:

verifed

Verified

(a) blured image (b,c)
blured image (d) z =...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents